Labor

The Labor tab allows you to set guidelines for labor allowances. Labor allowances are in hours or labor units. Items that are not applicable should be left blank. Items that not be included in an estimate (such as items that are not covered) should be set to “0” (zero).

ClosedTo set labor allowances

  1. From the Main window, click Profiles.

The Manage Profiles window appears.

  1. At the bottom of the window, under Profile Operation, select Add New Profile.
    Or, find the profile you want to change and select Change This Profile.
  2. On the Labor tab, in the Labor Allowances section, enter the allowance, in hours or labor units, for each of the available items . You can specify that labor for Frame Setup and Tint should use the Body labor rate by selecting @ Body for either of these two items.
  3. If applicable, type the allowance, in hours or labor units, for the Bumper Repair vs. Replace Alerts for an estimate.
  4. Click Save.

Reference

Labor Allowances

Clear Coat

Enter the guideline amount for Clear Coat.

Color Sand/Buff

Enter the guideline amount for Color Sand/Buff.

Frame Setup

Enter the guideline amount for Frame Setup.

 

@ Body

Select this check box if the amount charged on the estimate for Frame Setup is the Body Labor rate.

Any Repair Line

Enter the guideline amount for Any Repair Line.

Blend

Enter the guideline amount for Blend.

Tint

Enter the guideline amount for Tint.

 

@ Body

Select this check box if the amount charged on the estimate for Tint is the Body Labor rate.

Frame Repair

Enter the guideline amount for Frame Repair.

Bumper Repair vs. Replace Alerts

If Primary POI is Front or Rear

Enter the guideline amount for If Primary POI is Front or Rear.

If Primary POI is not Front or Rear

Enter the guideline amount for If Primary POI is not Front or Rear.